Canyon Residence Hall is a new student community providing amazing views, close access to food service and recreation venues, and a convenient location along the campus shuttle, pedestrian mall, and future STEM Building.

The 7-story residence hall is comprised of 942 beds. Amenities in the facility include a large student commons area, student lounge, student kitchen, seminar room, collaborative study rooms, package delivery pickup, gaming rooms, and laundry room.

Budget: $124M

Status: Construction – 28% Complete. Level 6 walls are in place and preparing for Level 7 floor.  MEP rough-in & exterior wall finishes on going.

Est. Construction Start: December 12th, 2023

Est. Construction Completion: July, 2025