Provenance / HR
Budget: $3,800,000
Status: Construction – 35% Complete. Framing & Drywall Installation underway.
Construction Start: July 16th, 2024
Est. Completion: December, 2024
Scope: Renovation of the existing Frost Bank building into offices for Human Resources.
Architect: PBK Architects
Contractor (CMR): The Fence Lady