Provenance / HR

Rendering of proposed interior renovations in the existing Frost Bank building

Concept Rendering of Building Interior

Budget: $3,800,000

Status: Construction – 35% Complete. Framing & Drywall Installation underway.

Construction Start: July 16th, 2024

Est. Completion: December, 2024

Scope: Renovation of the existing Frost Bank building into offices for Human Resources.

Architect: PBK Architects

Contractor (CMR): The Fence Lady