UFCU Stadium End Zone Complex Expansion
The UFCU Stadium End Zone Complex Expansion project will remodel a large portion of the existing south end zone complex by providing more breakout team rooms in the existing building, relocating the athletic performance center to open into the end zone, connecting the west and east concourse level balcony, and creating an alumni pavilion and deck on the roof of the building.
Budget: $42,000,000
Status: 80% Complete. Weight Room nearing completion. 3rd level hospitality interior finishes on-going. Training expansion preparing for tile. Warren Room is complete.
Start Date: October 3rd, 2023
Est. Completion: March, 2025
Scope: New weight and athletic training room, expand the current locker rooms, repurpose the existing weight room space for position meeting rooms, and create additional hospitality spaces.
Architect: Pfluger Architects, Inc.
Contractor (CMR): White Construction