JC Kellam Administration Building Reconfiguration
The JC Kellam Administration Building Reconfiguration project was the first major improvement to the building in over 30 years. This project converted the eleventh-floor meeting space into event space for various functions.
Budget: $8,900,000
Status: Complete.
Construction Start: March, 2023
Substantial Completion: April 22nd, 2024
Scope: This project converted the eleventh-floor into event, hospitality and meeting space for various functions, and replace existing roof.
Architect: Gensler
Contractor (CMR): Flintco