JC Kellam Administration Building Reconfiguration

JCK Conference Room

JCK Conference Room

The JC Kellam Administration Building Reconfiguration project was the first major improvement to the building in over 30 years. This project converted the eleventh-floor meeting space into event space for various functions.

Budget: $8,900,000

Status: Complete.

Construction Start: March, 2023

Substantial Completion: April 22nd, 2024

Scope: This project converted the eleventh-floor into event, hospitality and meeting space for various functions, and replace existing roof.

Architect: Gensler

Contractor (CMR): Flintco